如何提高长距离测量放线精确度

 
如何提高长距离测量放线精确度

如何提高长距离测量放线精确度

摘要:随着国家大力建设基础设施项目,集团公司承揽的管廊、道路项目越来越多,提高长距离测量放线的精确度已是迫在眉睫。测量放线是将图纸上的建筑物、构筑物,按设计与施工要求,测量到地面上预定的位置,作为建筑物的依据的过程。但是在测量放线的过程中,人们通过实际工作来求得真值时,不论测量仪器多么精密,测量进行得多么仔细,测量结果总是存在着差异。这就是因为我们的测量结果中存在误差的缘故。为了使测量放线的成果真实可靠的反映测量对象,就应学习和尽量掌握误差的规律,使其在一定条件下尽量减小。

关键词:长距离;测量放线;精确度

Abstract: Along with the country to promote the construction of infrastructure projects, group company contracted pipe gallery, the road project is increasing, improve long distance measurement and setting-out accuracy is imminent. Measurement line is drawing on the buildings, structures, according to the requirements of design and construction, measuring ground to a predetermined position, as building based on the process. But in the surveying process, people through the practical work to obtain the true value, no matter how precision measuring instruments, measuring how carefully, there are differences of measurement results. This is because our measurement results in error. In order to make the measurement line results reliable reflect the measurement object, we should study and try to master the law of error, which under certain conditions to minimize.

Key words: long distance; surveying; precision

我公司承揽的沧州渤海新区化工管廊工程,为沧州市渤海新区重点工程项目之一,全长2576.2米。本工程质量目标为创省优工程,对工程质量要求较高。长距离测量放线精确度直接影响工程的质量,其中钢结构安装的精度取决于地脚螺栓的预埋精度,而在较大范围内的地脚螺栓预埋精度则由测量放线的精度所决定。下面就如何提高长距离测量放线精确度进行阐述:

http:///
一、工程现状及分析

为贯彻公司质量方针,坚持预防为主、严格过程控制,争创河北省优质工程“安济杯”。渤海新区化工管廊工程分三段施工,通过对其中一段773轴—778轴,基坑位置及预埋螺栓的调查,发现长距离测量放线精确度不高,存在偏差现象,很大程度上影响了工程质量和施工进度,对工程创安济杯奖造成了一定的影响。

经过调查分析发现,长距离测量放线精度不高、存在偏差的问题主要产生于横向累计偏差。建立基准线网络,各基准线之间的平等度、垂直度均能达到很高的精度要求。利用网格基线来控制设备地脚螺栓的预埋偏差,减少误差传播量,从而保证设备安装精度。