T梁预应力管道维修补浆技术
摘要:预应力管道补充灌浆工艺是在我省第一次使用,在有关专家的指导下,笔者和相关技术人员经过探讨和摸索,成功完成了本工程的维修工作,预应力管道补充灌浆后经检验是密实的,该工艺是成功和可靠的。防腐和裂缝处理为成熟工艺,本文不在赘述。
关键词:T梁养护维修;预应力管道后补浆;施工工艺
Abstract: The prestressed duct grouting process is added in our province the first use; in under the guidance of experts, the author and the relevant technical personnel after the discussion and exploration successfully completed the repair project job, the prestressed duct grouting is added after the inspection of compaction, the process is successful and reliable. Corrosion and crack treatment is a mature technology, this article is not in the here.
Key words: maintenance and repair of T beam; prestressed pipe filling slurry; construction technology
工程实例概况
德州某桥,桥梁全长356m,半幅桥面宽度为0.5米护轮带+11.25米行车道+1米防护栏。上部构造为14孔标准跨径25米的预应力钢绞线混凝土T型组合梁,其中单片主梁高1.6米,翼缘宽2.1米,马蹄宽0.4米,腹板宽0.2米;单幅横向6片主梁籍以3道横隔板和现浇桥面板以及8cm现浇混凝土桥面铺装连成整体。
该桥自建成通车运营以来,在桥梁检查中发现部分主梁马蹄及腹板(0~L/4,3L/4~4L/4)部位出现不同程度的病害、缺损,经检测部门检验,T梁部分预应力管道内未灌水泥浆或灌浆不满,为防止预应力的损失,防止预应力筋的锈蚀,桥梁管养部门和检测部门决定对该桥进行维修处理。主要维修内容如下:
(1)预应力管道补充灌浆;
(2) 修补缺损混凝土,粘贴玻璃丝布防腐;
(3)裂缝处理,包括裂缝压力灌浆和封闭处理。
2.预应力管道补充灌浆工艺
2.1、根据原设计图纸,在梁腹板进行预应力筋定位,放样。标注清楚波纹管距梁腹板表面的设计厚度和锚下砼中螺旋筋的位置。开孔检查时,应避开该螺旋筋区域。