乌北750千伏变电站双母线双分段改造

 
乌北750千伏变电站双母线双分段改造

乌北750千伏变电站双母线双分段改造

摘要:目前乌北750千伏变电站不仅承担着疆电外送的重要任务,还担负着乌鲁木齐市及周边县市的重要负荷输送,由于系统容量和负荷增长迅速,已不满足安全稳定运行的需要,因此需将原有220千伏双母线改造为双母线双分段结构,使之满足安全运行的要求,同时也增强运行的灵活性。

关键词:乌北750千伏变电站双母线双分段改造 安全运行 母线轮停

Abstract: at present, the North 750000 volts transformer substation not only bear the important task of Xinjiang electric delivery, is also responsible for Urumqi city and the surrounding counties and cities important load transfer, since the system capacity and load growth is rapid, already did not satisfy the need of safe and stable running, so the original 220000 volt dual bus transform for double bus with two sections structure, so as to meet the requirements of safety operation, but also enhance the flexibility of operation.

Key words: the North 750000 volt double busbar sectional reconstruction security operating bus wheel stop

乌北750千伏变电站作为新疆-西北联网通道的重要环节,其220千伏开关站于2008年6月投运,2010年11月750千伏升压联网成功,自此新疆电网结束孤网运行的历史。

http:///
一、施工任务简介

本次双母线双分段改造一次工作包括新增分段、母联、母线等一次设备(图

一),由于220千伏管型母线对地距离为9.35米,分段间隔设备安装后高度在

6.8-7.8米,安全距离不足(图二),因此必须在母线轮停后进行安装。二次工作包括对已投运220kV间隔及母线保护二次回路进行改造,并对母线保护进行升级。原母线保护配置为:220kV 1、2号保护小室各有两套母线保护,2号小室内的母线保护没有运行,接入的所有单元二次回路转接至1号小室母线保护。本次母线保护改造需将1、2号保护小室母线保护间的联络电缆拆除,即1号保护小室内母线保护对应Ⅰ/Ⅲ母,2号保护小室内母线保护对应Ⅱ/Ⅳ母(图三)。

(图一 电气主接线图)

(图二 分段间隔断面图)