公伯峡水电站右岸旋流泄洪洞原型水力学观测试验
摘 要:公伯峡水电站右岸泄洪洞是在大量模型试验研究、理论分析及结合本工程地质和运行要求特点的基础上建成的,鉴于理论研究旋流洞内的复杂水流运动难度较大,研究过程中需引入一些假定,这些假定与实际情况会有一定的差异,而试验研究又存在缩尺效应,所以,进行旋流式消能工程的原型观测研究具有十分重要的学术价值和工程意义。
关键词:公伯峡水电站右岸旋流泄洪洞原型水力学观测试验
Abstract: The spillway tunnel on the right bank of Gongboxia Hydropower Station is built on the researches and theoretical analysis of a large number of model tests, and the characteristics of this engineering geology and operation requirements. As the difficulties in theorectical research in the complex flow movement inside the rotational folw are large, some assumptions should be introduced in the process of research, which have difference from the acrual situation, and scale effects exist in tests results. Therefore, it is of great academic value and engineering significance to conduct the prototype observation research of the rotational flow energy dissipation engineering.
Key words: Gongboxia Hydropower Station; right bank rotational flow spillway tunnel; observation test of prototype hydraulics
http:///
一、概述
公伯峡水电站右岸水平旋流式泄洪洞是我国建成的第一个大规模的水平旋流洞。泄洪洞总水头110m,校核洪水位和设计洪水位工况下的泄流量分别为1090m3/s和1060m3/s,泄洪功率较高,技术难度大。自上个世纪60年代以来,国内外对旋流式消能工程进行了大量的试验研究,但是一直没有工程已建和运行的报导。公伯峡水电站右岸泄洪洞是在大量模型试验研究、理论分析及结合本工程地质和运行要求特点的基础上建成的,鉴于理论研究旋流洞内的复杂水流运动难度较大,研究过程中需引入一些假定,这些假定与实际情况会有一定的差异,而试验研究又存在缩尺效应,所以,进行旋流式消能工程的原型观测研究具有十分重要的学术价值和工程意义。
水力学原型观测的实施可分为三个阶段:预埋电缆情况调查、观测仪器埋设和过水试验。过水试验共进行了三次,于2006年8月12日、16日和18日进行,三次试验工作闸门全开运行的时间分别是20分47秒、21分09秒和60分07秒。
二、 测点布置