采用灌浆法处理碾压混凝土大坝坝体渗水问题
摘要:碾压混凝土作为一种新的筑坝技术,由于其具有水泥用量少、施工速度快、工程造价低、温度控制简单、施工设备通用性强等特点,已被广泛应用于水电工程,并且在技术上日益成熟。但与此同时,碾压混凝土除存在一般普通混凝土质量问题外,由于其本身的特殊性,还存在一些其他质量问题,如密实度不够,层间结合不良、渗漏以及温度裂缝等,有些问题已在某种程度上制约了碾压混凝土技术的进一步发展,已引起了各方面的关注和研究。本文着重论述四川某大型碾压混凝土大坝坝体渗水处理的方法。
关键词:灌浆法;处理;碾压混凝土;坝体渗水
Abstract: RCC(roller compacted concrete), a new dam construction technique, has been widely used in hydropower engineering for its features of small amount of cement, fast speed of construction, low construction cost, simple temperature control, versatile construction equipments, and it has being increasingly skilled in technique. While in addition to the quality problems existing in common concrete, the RCC due to its own characteristics has some other quality problems such as insufficient density, poor binding between layers, seepage and temperature cracks. And some of those has brougt restriction to the concrete’s further development to some extent, which obtains attentions and research from all aspects. In this paper, the water seepage processing methods of a large-scale RCC dam in Sichuan province are discussed.
Key words: grouting; processing; RCC; dam seepage
施工概况
该大坝工程的主要任务是蓄水发电,水库正常蓄水位1330.00m,死水位1328.00m,总库容7.6亿m3,属日调节水库,为一等工程,主要水工建筑物为1级,次要建筑物为3级,临时建筑物为4级。电站枢纽建筑物主要由左右岸挡水坝、中孔坝段和溢流坝段(为碾压混凝土重力坝)、消力池、右岸引水发电系统组成,右岸地下厂房装机4台600MW机组,总装机容量2400MW。大坝内主要布置三层坝体排水廊道,分别是1#坝体排水廊道在EL1295,2#坝体排水廊道在EL1254,3#坝体排水廊道在EL1205。
大坝初期蓄水于2011年11月完成, 2012年2月实现中孔下闸蓄水,2012年3月水位到达1317.0m,2012年7月水位到达正常蓄水位EL1330.00,通对多次对大坝坝内廊道及坝后观察,发现大坝坝内现浇廊道局部不密实部位、预制廊道拼装缝、冷却水管预留孔、坝后层间及坝段横缝处均有不同程度的渗水,部分坝基坝体排水孔内排水量偏大,据观测仅大坝右岸渗水量就超过100m3/h。
坝体渗水原因分析
从渗水统计情况来看,右岸大坝渗水点主要集中在EL1254以下主帷幕灌浆
bbs.99jianzhu.com内容:建筑图纸、PDF/word 流程,表格,案例,最新,施工方案、工程书籍、建筑论文、合同表格、标准规范、CAD图纸等内容。