吹填造陆工程施工工艺及质量控制探讨
摘要:近年来,为解决土地稀缺问题和促进沿海经济发展,吹填造陆被越来越多的运用到施工工程中。本文结合笔者参与的某港区吹填工程施工实践,谈谈吹填造陆工程施工工艺,并从定位挖泥船、控制开挖深度、控制吹填区的平整度几方面探讨工程的质量控制。
关键词:吹填造陆;施工工艺;质量控制
Abstract: in recent years, to solve the problem of the scarcity of land and promote the coastal economic development, land building on filling the more and more applied to the construction of the project. The author discusses the port in a reclamation works construction practice, talk about on filling the land building project construction process, and from the orientation, control mire ship excavation depth, blow the flatness control fill several aspects of the engineering quality control.
Key words: blow fill created land; The construction technology; Quality control
近年来,为解决土地稀缺问题和促进沿海经济发展,吹填造陆被越来越多的运用到施工工程中。吹填造陆是将一定比例的砂、浆泥和海水混合成浆体,并用吹管将其输送至制定区域,经过排水固结形成陆域的土地开发技术。本文结合笔者参与的某港区吹填工程施工实践,谈谈吹填造陆工程施工工艺及质量控制。
1 主要工程概况
该港区造陆工程吹填区长1568m、宽1448m,面积227万m2,吹填量约1200万m3。由于吹填面积较大,为方便吹填,将其沿着南北方向修筑的隔埝分成东西两个区。施工时先吹填东区,再吹填西区。在位于吹填区以东3.2km处取泥,长1570m、宽500m,面积为78.5万m2。根据取泥区地质报告分析,取泥区地质至上而下分别为:淤泥、淤泥粉质粘土、粉质粘土、粉砂、粘土。粉土、粘土在地下﹣14m至﹣20m之间。
本次吹填工程对施工技术要求为:+5m~+6m的吹填高程,不低于14kN/m3的吹填表面土容量,不低于80%的表层含水率。
2 主要施工方法
2.1绞吸船进场、布置