乐昌峡水利枢纽碾压混凝土重力坝变态混凝土质量控制
摘要:乐昌峡水利枢纽碾压混凝土重力坝在变态混凝土的应用上采用拌和楼直接拌制变态混凝土用于大体积变态混凝土施工取得良好的效果,有效控制浇筑质量和保持浇筑连续性。业主及监理实行每仓碾压混凝土浇筑旁站施工,并由第三方检测单位全程跟踪检测、控制,确保变态混凝土施工质量。
关键词:碾压混凝土重力坝;变态混凝土;施工质量控制
Abstract: The Lechang gorge roller compacted concrete gravity dam in the distorted concrete applications uses the mixing plant directly mixing metamorphic concrete for large volume distorted concrete construction and achieves the good results, effectively controls the pouring quality and maintain pouring continuity. The owner and supervision do the roller compacted concrete pouring every warehouse site construction, and by the third detection unit tracking ,detecting and controlling, to ensure the concrete construction quality.
Key words: metamorphosis roller compacted concrete gravity dam; distorted concrete; construction quality control
1. 工程概况及变态混凝土的特性
1.1工程概况
乐昌峡水利枢纽工程等别为Ⅱ等大(2)型,其主要建筑物拦河坝的级别为2级,次要建筑物的级别为3级,临时性建筑物为4级。拦河坝为碾压混凝土重力坝,河床中央布置5孔溢流坝,每孔净宽12m,堰顶高程134. 8m,闸孔孔口尺寸为12mx10.7m。坝顶高程164.6m,最大坝高84.6m,坝顶长256.0m,其中溢流坝段长78.0m,左岸非溢流坝段长96.0m,右岸非溢流坝段长82.0m。
乐昌峡水利枢纽碾压混凝土重力坝,混凝土浇筑43.2万m3,碾压混凝土浇筑方量为27.6万m3。在施工中,变态混凝土得到广泛应用,总方量达1.86万m3。碾压混凝土坝段上游模板边、下游坡面1.5m范围内、预制廊道周围、上下游止水铜片埋设周边及振动碾碾压不到的部位全部采用浇筑变态混凝土。
2.变态混凝土的施工现场控制
变态混凝土是指在不改变碾压混凝土基本特性和运输条件下,通过在碾压混凝土层面注入适量的水泥浆或水泥砂浆和强力插入振捣使碾压混凝土改性,从而获得既能增强层面结合又能改善混凝土密实性的新型混凝土。
乐昌峡水利枢纽碾压混凝土重力坝施工过程中,每仓碾压混凝土浇筑均安排